Tucson International Airport
Project Start Date: September 24, 2012
Duration: October 30, 2012
WORK CONSISTS OF: Asphalt pavement repairs, crack sealing, sealcoat application, and re-striping. See Attached Diagram.
Phase #5
- Runway 11R/29L will be closed for the duration of project.
- Taxiways A5, A6, A11, A13 and A15 south of RW 11L/29R will be closed.
- Taxiway A8 will be available for aircraft movements between "blue hanger" to TW A.
- Taxiway D is available through October 18, 2012.
Phase #6
-Taxiway D closed from October 18-19, 2012.
-Taxiway A5, A8, and A13 will be available for aircraft movements.
Any changes will be updated through NOTAMs and Project Advisories. Please use Extreme Caution while in the area.
|