Sealcoat Runway 11R/29L and Connecting Taxiways

Related Document: SPD-KMC28012092008570.pdf

 

 
 
                             

 

                                                    Tucson International Airport

               

Project Start Date:  September 24, 2012

Duration:  October 30, 2012 

WORK CONSISTS OF:  Asphalt pavement repairs, crack sealing, sealcoat application, and re-striping.  See Attached Diagram.

Phase #5 

- Runway 11R/29L will be closed for the duration of project.

- Taxiways A5, A6, A11, A13 and A15  south of RW 11L/29R will be closed.

- Taxiway A8 will be available for aircraft movements between "blue hanger" to TW A.

- Taxiway D is available through October 18, 2012.

 

Phase #6

       -Taxiway D closed from October 18-19, 2012.

       -Taxiway A5, A8, and A13 will be available for aircraft movements.

      

Any changes will be updated through NOTAMs and Project Advisories.  Please use Extreme Caution while in the area.                                                   

PRIMARY PROJECT CONTACT:

Routine Project Information:               Mark Staszak (520-573-8014)

Construction Emergencies (24/7):         Mark Staszak (520-573-8014) OR

Airport Operations Inquiries:              Danette Bewley (520-573-4820)

Page Via TAA Communications Center (520-573-8182 or 8111)